B2 Destack Shed

06 August 2016

Adam, MVH Special Projects Advisor, spent a month at Kogan – Bremar 2 Gas Fired Power Plant providing Project Management (Safety, Design, Construction process and Project delivery). Adam delivered the project, Destack shed; the second only ever built in Australia and the first ever built with an operable sliding roof a massive 10 weeks ahead of an all ready accelerated programme. Original programme was 30 weeks and was delivered in 5 weeks with zero defects and zero incidents. Check out This impressive YouTube Time Laps Video

MVH Group’s incidents free days are now in excess of 2122 days which is outstanding.

Project was delivered in conjunction with FKG Group (PC) and Arrow Energy (Client).
As you can see by the pictures, this is a BIG project.